EUCLID Catalog    Library Info
     Research Assistance
 
Research Guides
Research FAQs
EndNote Use
Ask A Reference Question
Contact a Subject Librarian
About Our Collections
 

    Borrowing / Circulation
 
Requesting and Borrowing
Renew Materials
About Interlibrary Loan
 

    Other Services
 
Workshops
Instruction for Classes
Computing in the Library
Contacts for Assistance
 

    Resources Developed at Emory
 
Digital Library Initiatives
Open Source Projects
Library Publications
 
 


EUCLID Databases e-Journals Reserves Direct

Level 7 Retrieval FAQs Quick Retrieval

Before

After

New Lounge

 
   
Schedule
   
May 27, 2008

Level 7 closes. Books with call numbers F1001 through HJ (which include Anthropology, Business, Canadian history, Economics, Geography, Latin American history, Statistics, and U.S. local history) move to the Storage Library.

During the move, the collection will be inaccessible for approximately TWO (2) weeks.

June 16, 2008 Requests for retrieval activated, with deliveries on Monday thru Friday.
Mid June 2008 - January 2009 Abestos removal, shelving removal, carpeting, painting, and new compact shelving installed.
October 25 - December 6, 2008 Saturday deliveries. Requests placed after 12 noon on Fridays and on Saturday mornings will be delivered to campus Saturday afternoons after 3:00 p.m.
January 5, 2009 Books move back to Level 7 and are inaccessible.
January 26, 2009 Level 7 reopens to the public
   
Project Overview  

The Stack Tower conversion to compact shelving will increase shelving capacity in the Woodruff Library Stack Tower in order to keep as much of the library's collection as possible on the central campus and accessible to users. Since 2003, Level 4, 5 and 6 renovations have been completed. Renovation for level 7 will begin in May 2008 and will be completed in Jan. 2009. The process takes approximately nine months for each floor. As more stack floors are renovated, the capacity of the Stack Tower will eventually increase by 50%. It now holds 1.8 million volumes.

New carpet, paint, and ceilings will make each floor more inviting and comfortable. New lounge areas near the elevator lobbies will feature comfortable chairs and couches and views of the Baker Woodland. New features on Level 7 also will include three group study rooms. Additional electrical outlets also will be installed.

Renovation includes the addition of an ADA-compliant restroom adjacent to new wheelchair accessible open carrels and closed studies. A new fire suppression sprinkler system will be installed on each floor for the security of the collections and to ensure personal safety.

The library is enthusiastic about this cost-effective, user-centered approach to accommodating the growth of its physical collections. We apologize for the temporary inconvenience as we continue to improve services and access to collections.

If you have questions about the project, retrieval services, your borrowing privileges, electronic resources, or storage, please contact us at WoodLibRenovation-L@listserv.emory.edu.

 